March 31, 2025Milestone’s hit at the A428
March 2025
Milestone’s hit at the A428
A428 Black Cat update: The formwork for the east abutment wall of Bridge Structure ST03 has been completed, and yesterday it was filled with 200m3 of concrete. This formwork will be removed in the next few days to prepare for the west abutment wall. Subsequently, the large bridge beams will be delivered to the site for installation in preparation for the Paraslim formwork.